TURKCE | Home Page | Site Map
                 




I. ON TIME DELIVERY PERFORMANCE: (35 points / 100 points)

On Time Delivery Performance = ∑ (Quantity delivered at On Time Delivery Period) / ∑ (Purchasing Order Quantity) x 100

* On Time Delivery Period: Week on purhasing order and one week before.


II. QUALITY PERFORMANCE: (45 points / 100 points)

o QUALİTY PERFORMANCE AT ENTRANCE TO WAREHOUSE:
(22,5 points / 100 points)

Quality Performance at Entrance to Warehouse = ∑ (Quality Points ) / Number of Stock Receipts

Calculation will be done according to quality decisions given by quality control department. Quality decisions and points used in Evyap are given below.

» Accepted: 100 points
» Warning: 75 points
» Use By Selecting: 50 points
» Conditional Acceptance: 25 points
» Rejection: 0 puan


o QUALİTY PERFORMANCE AT PRODUCTİON: (22,5 points / 100 points)
Quality Performance at Production = (1 - ∑(Total Cost of material caused errors in production) / ∑(Total purchasing amount of last 12 months)) x 100



III. PRİCE PERFORMANCE: (10 points / 100 points)

Supplier prices will be compared with average of all price offers received in the period. Difference between supplier price and average of all price offers, will be divided to average price offers. This price difference percentage (+/- %15 ), will be graded linear between 0-100 points.





IV. SERVİCE PERFORMANCE: (10 points / 100 points)

Service Performance points will be given according to Supplier Service Performance Evaluation Survey results.

No Question Weight
1 Supplier approach to daily operational problems and response speed 20%
2 Financial conditions and general reputation of the supplier 20%
3 Performance of the supplier on new product development 20%
4 Technology level of the supplier 20%
5 Information sharing level of the supplier 20%



 